Commercial Structured Cabling RFP Checklist
Define testing, pathway, labeling, and closeout before you send the drawing set — so the quotes you get can actually be compared.
Written by Patrick Atkins, founder of Atkins Tech Solutions. Last reviewed August 29, 2026.
1. Project basics
Identify the commercial conditions that change price and schedule before bidders guess.
- site address
- building type
- new construction / renovation / occupied
- bid date
- award target
- rough-in window
- trim-out window
- turnover/opening date
- working-hour restrictions
2. Drawings and counts
Counts belong in the bid package, not in a later addendum after everyone has already priced a guess.
- architectural plan
- reflected ceiling plan
- furniture plan
- telecom drawings
- device/drop schedule
- workstations
- APs
- cameras
- access doors
- AV/conference rooms
- printer/POS/equipment drops
3. Copper specification
Name the cable, termination, and hardware series so bidders are pricing the same plant.
- Cat6 / Cat6A
- UTP / shielded
- riser / plenum
- color
- T568A / T568B
- jack manufacturer/series
- patch-panel manufacturer/series
- faceplates
4. Fiber
If fiber is in scope, define strand count, connectors, and test method in the RFP.
- OS2 / OM3 / OM4
- strand count
- connector type
- MDF-to-IDF route
- spare strands
- splice vs pre-terminated
- enclosures
- loss-test requirement
- OTDR requirement
5. Telecom rooms
The closet is part of the cabling system. Leave rack, plywood, bonding, and switch ownership explicit.
- MDF/IDF locations
- rack/cabinet size
- wall vs floor rack
- plywood/backboard responsibility
- patch panels
- management
- ladder rack/tray
- bonding responsibility
- UPS/PDU responsibility
- switch owner
6. Pathway
Pathway responsibility is one of the most common sources of incomparable cabling bids.
- J-hooks
- tray
- conduit
- sleeves
- core drilling
- existing pathway reuse
- EC vs LV pathway responsibility
- hard ceilings
- outdoor/underground
- lift requirements
7. Penetrations / firestop
Rated walls need an owner, a system, and documentation — not a punch-list argument.
- penetration responsibility
- firestop responsibility
- required system/manufacturer
- rated-wall documentation
8. Testing
Define the test level before pricing. Verification, qualification, and certification are different.
- verification
- qualification
- certification
- permanent link vs channel
- test standard
- required tester/platform
- calibration
- PDF/native format
- failed-link remediation
- fiber loss/OTDR
9. Labeling
A plant without a naming convention is not finished, even if every drop links.
- naming convention
- TIA-606 or owner standard
- room/jack/panel ID
- both-end cable labels
- patch-panel labels
- device IDs
10. Closeout
State the evidence the owner and IT team must receive.
- test results
- port schedule
- as-builts/redlines
- photos
- rack elevation
- device list
- warranty/O&M
- punch list
- handoff/training
11. Commercial requirements
These items change price even when the drop count does not.
- permits
- prevailing wage
- certified payroll
- union
- badging
- background checks
- OSHA
- insurance limits
- additional insured
- lien waivers
- payment terms
- retainage
12. Furnished-by responsibility
Identify owner/GC/EC/IT/LV responsibility for switches, APs, cameras, racks, patch panels, cable, jacks, UPS, mounts, and controllers.
FAQ
Frequently asked questions
- Will ATS review a cabling bid package before we release it?
Yes. Send the plan set, Division 27/28 specifications, addenda, device schedule, bid date, and project location.
Related pages
Guides
Get started today
Ready to start your project?
Tell us about your building, timeline, and scope. we respond to quote requests within one business day.
PA HIC Registration #PA213204 · Commercial Low-Voltage Contractor · Fully Insured · 5.0 Google rating